Transformers, agricultural machinery, headers, industrial equipment — from China, India, Türkiye, the EU or the USA. A turnkey international route: securing, permits in every transit country, customs clearance, insurance — and you see the cargo at every transshipment.
Trusted by more than 80 importers
They promised 45 days — and got stuck on route approvals and permits. Meanwhile everything on your side is ready for start-up.
Secured “by eye” — an expensive unit arrived with a defect worth hundreds of thousands.
Escort, transshipments and special equipment popped up — the final invoice is far above the estimate.
One miscalculation in the scheme means a project standing still for millions and equipment damaged for hundreds of thousands.
Issuing permits, approving the route and the clearance corridor. The permit side is on us.
The route scheme, measuring bridges and power lines, escort and police support where required.
The relevant authorities in the Netherlands, Germany and Poland. Securing rules, cargo classes, a full set of documents.
A multimodal scheme: flat rack / OOG / RO-RO / breakbulk — ways to move what doesn’t fit a container. Safe corridors — no russia, no Caspian.
Securing calculations, an independent survey before and after — so the cargo isn’t damaged in transshipment.
On the real value of the cargo + war risks.
Storage systems and transformers don’t fit the standard, and the substation start-up is tied to a date — a delay costs a lot.
A crane or chassis stuck waiting for transit permits, or delivered with a defect — the site stands still while the machinery and the rent run at a loss.
A complete line travels in batches from different ports to a single deadline — any link drags the rest with it.
This is not a badge for the website. PLA is an international network of vetted project logistics providers, and your complex route gets access to specialists at every point of it:
Annual PLA summit · 2026 · Ho Chi Minh City, VietnamLeave a request. In 30 minutes we’ll find where you can save time and stop losing money. No obligations, no sales pitch.
The production line hung in China 4 days before Chinese New Year. We took the whole of China on ourselves, found special platforms and open-tops in different ports, and when we saw a buffer, moved part of the oversized cargo from trucks to rail.
40 containers · 11 special · on timeThe jib is usually removed — and that makes two pieces: two low-loaders, two customs entries. We secured it on the crane as a single structure within the gauge and pushed the wording through in the bill of lading.
$6,150 saved ($3,650 sea + $2,500 without a second low-loader)Real cargo we have moved: mobile cranes, power transformers, energy storage systems and production lines — from the plant in China to the site in Ukraine and the EU. Hover or tap to open.
Oversized is not a property of the cargo but a property of the route. The Ukrainian limits (clause 22.5 of the road rules) and the European ones (Directive 96/53/EC) do not match, so the same combination can be legal in Ukraine and oversized in Poland. The common market mistake is to take one number off the internet and treat it as universal.
| Parameter | Ukraine (clause 22.5 of the road rules) | EU (Dir. 96/53/EC) |
|---|---|---|
| Width | 2.6 m | 2.55 m · 2.60 m for conditioned bodies |
| Height | 4.0 m · container carriers on designated routes — 4.35 m | 4.0 m |
| Length of a single truck | 12 m | 12 m |
| Length of a road train | 22 m | 16.5 m articulated vehicle · 18.75 m road train |
| Rear overhang | 2 m | governed by national rules |
| Gross weight, 2-axle tractor + 3-axle semi-trailer | 40 t | 40 t · 42 t in intermodal with an ISO container (44 t — only with a 3-axle tractor) |
| Single axle load | 11.5 t | 10 t non-driving · 11.5 t driving |
Swipe the table sideways →
Exceeding even one parameter makes the shipment oversized — and from there a permit is required in each country of the route separately. Ukrainian sources routinely confuse these two columns: 2.55 m in width is the EU norm, not the Ukrainian one, and 4.3–4.5 m in height is not a norm anywhere. For agricultural machinery outside built-up areas in Ukraine the width is 3.75 m; the weight tolerance is 2%.
Under clause 22.5 of the road rules, cargo is oversized if it is wider than 2.6 m, higher than 4.0 m, longer than 12 m for a truck or over 22 m for a road train, or overhangs the rear by more than 2 m. For container carriers on designated routes the height limit is 4.35 m; for agricultural machinery outside built-up areas the width is 3.75 m.
Width: 2.6 m in Ukraine against 2.55 m in the EU (2.60 m in the EU is allowed only for conditioned bodies). Road train length: 22 m in Ukraine against 18.75 m in the EU, with an articulated vehicle at 16.5 m. Height is the same — 4.0 m. So a combination that is legal on a Ukrainian road already needs a permit on the Polish or German leg — and the other way round. The gauge is checked against the norm of the country whose road you are on right now, not the country of destination.
In every one. There is no single European oversized permit — each country of the route issues its own, with its own procedure, its own processing time and its own limit values. For a typical “EU port → Ukraine” leg that is a chain: the port country, every transit country, Ukraine. That is why we agree the route before booking, not after the vessel arrives: the longest processing time in the chain sets the departure date.
A pilot car — at a width over 3.5 m or a length over 24 m (clause 27). A police escort — at a width over 3.75 m, a length over 30 m, or when the route requires driving into the oncoming lane (clause 28).
Weight above 60 t. At that weight the road owner may require surveys and reinforcement of engineering structures — bridges and overpasses — at the expense of the party ordering the transport. That amount has to be budgeted before the contract is signed, not after.
For Ukraine: a single permit covers one trip, and for a recurring route with the same vehicle it is issued for up to 3 months. In EU countries the terms are their own — from a single trip to annual permits for defined corridors, and each one is counted separately.
Updated: 27 July 2026